Construction Ready to Begin Again on Roundabout
March 26, 2015 Leave a comment
Work is set begin again soon on the roundabout at the Highway 32/77 junction. “The contractor plans on returning to the project on Monday, April 6th,” said Kevin Domogalla of the Nebraska Department of Roads.
The workers will begin by grading and surfacing the temporary road. “That work will take approximately three weeks,” Domogalla stated.
After that, the east left of the intersection, Highway 32 towards Tekamah, will be closed after the temporary road is open to traffic. “The contractor will then begin constructing the roundabout. Highway 77, north and south, and west Highway 32 to West Point, will remain open during all phases of construction,” said Domogalla.
Stay tuned to Kat Country Hub for more information as the contractor’s schedule is updated.