Roundabout at Hwy 77/32 to Open October 2nd
September 21, 2015 Leave a comment
The roundabout at Hwy 32/77 is nearing a completion date, hopefully. There have been many delays is progress since the project started quite a long time ago. The Project Manager, Jeff Francis, provided a detailed time frame for the next couple of weeks until it is completed.
“The contractor informed me that they will be ready to open the roundabout on October 2nd,” stated Jeff Francis.
Below is the schedule of work to be completed before the roundabout is opened.
Upcoming work—
Pavement markings will be installed today,
Median surfacing is scheduled to be completed by 9/26/15
Begin high mast tower foundation work on 9/23/15
Set the high mast tower on 10/1/15 (if the concrete foundation attained adequate strength)