Update on Roundabout at Highway 32/77 Junction


The roundabout at the junction of Highway 32/77 was projected to be completed at the end of this month. The date has been pushed back at least two weeks.

“The contractor is 2 weeks behind their schedule—that puts us into the middle of August; inclement weather will extend the delay.

They hope to resume the paving operation late next week,” stated Jeff Francis, project manager.

Stay tuned to Kat Country Hub for further updates.

 

Unknown's avatarAbout katcountryhub
I am a graduate of Northeast Community College with a degree in journalism. I am married to Jeff Gilliland. We have two grown children, Justin and Whitney and four grandchildren, Grayce, Grayhm, Charli and Penelope. I will be covering Lyons, Decatur, Bancroft and Rosalie and am hoping to expand my horizons as time progresses!